HVDC DolWin3
| HVDC DolWin3 | |
|---|---|
![]() Location of HVDC DolWin3 | |
| Location | |
| Country | Germany |
| General direction | north–south |
| From | Platform DolWin Gamma |
| Passes through | North Sea |
| To | Dörpen/West substation |
| Technical information | |
| Type | submarine cable, subsoil cable |
| Type of current | HVDC |
HVDC DolWin3 is a high voltage direct current (HVDC) link to transmit Offshore wind power to the power grid of the German mainland. The project differs from most HVDC systems in that one of the two converter stations is built on a platform in the sea. Voltage-Sourced Converters with DC ratings of 900 MW, ±320 kV are used and the total cable length is 160 km.
The overall project is being built by Alstom with the cables supplied by Prysmian and offshore platform by Nordic Yards. Construction commenced on the onshore converter station at Dörpen West in May 2014 [1] and on the offshore platform in October 2014.[2][3] As of summer 2015 the platform was being fitted out and the first converter transformer was installed on 17 July 2015.[4] The project was handed over to its owner, TenneT, in 2017. The grid connection is in operation since September 2018.[5] A fund managed by Copenhagen Infrastructure Partners has invested in this offshore transmission platform.[6]
Connected wind farms
- Merkur (396 MW)
- Borkum Riffgrund II (448 MW)
See also
- High-voltage direct current
- Offshore wind power
- HVDC BorWin1
- HVDC BorWin2
- HVDC BorWin3
- HVDC DolWin1
- HVDC DolWin2
- HVDC HelWin1
- HVDC HelWin2
- HVDC SylWin1
References
- ^ Construction begins on offshore grid connection DolWin3 Sun & Wind Energy, 27 May 2014.
- ^ Yards Starts Building DolWin Gamma, Offshore Wind.biz, 9 October 2014.
- ^ Nordic Yards Holds DolWin Gamma Dock Laying Ceremony, Offshore Wind.biz, 2 February 2015.
- ^ Alstom and TenneT to reach another important milestone in the offshore DolWin3 project, Alstom Press Release, 17 July 2015.
- ^ "DolWin3 - TenneT". www.tennet.eu. Retrieved 2021-05-11.
- ^ "Artemis I, Germany - Copenhagen Infrastructure Partners". Retrieved 2021-05-11.
External links
- Description of project on TenneT website (in German).
- Dolwin3 Archived 2015-02-13 at the Wayback Machine, Alstom website.
Content Disclaimer
Informasi ini disarikan dari Wikipedia dan disajikan kembali untuk tujuan edukasi. Konten tersedia di bawah lisensi CC BY-SA 3.0. Kami tidak bertanggung jawab atas ketidakakuratan data yang bersumber dari kontribusi publik tersebut.
- The information displayed on this website is sourced in part or in whole from Wikipedia and has been adapted for the purpose of restating it. We strive to provide accurate and relevant information, however:
- There is no guarantee of absolute accuracy. Wikipedia is an open, collaborative project that can be edited by anyone, so information is subject to change.
- It is not intended to constitute professional advice. The content displayed is for informational and educational purposes only. For important decisions (e.g., medical, legal, or financial), please consult a professional.
- Content copyright. Wikipedia is licensed under the Creative Commons Attribution-ShareAlike License (CC BY-SA). This means that content may be reused with appropriate attribution and shared under a similar license.
- Responsible use. Any risk arising from the use of information from this website is entirely the responsibility of the user.