Western Resource Adequacy Program
The Western Resource Adequacy Program (WRAP) is an electricity planning and sharing agreement between electric utilities of the Western Power Pool. Its goals are to improve regional reliability and adequacy while decreasing costs by moving utilities from an individual utility framework to a regional approach. Program operations are based in Oregon.[1][2]
The agreement calls for "forward showing" in which utilities must forecast demand seven months in advance and prove that they have secured access to sufficient supply to meet that forecast along with sufficient transmission capacity to deliver that supply. It also calls for an "operational program" where utilities with an unforeseen near-term deficit can call out to other utilities for spare capacity via a regional marketplace. Lastly, it calls for "enforcement" in which utilities can be charged for noncompliance.[1][2][3]
The initial phase of the program is voluntary. As of April 2023, 22 utilities from Canada and the USA have committed to this phase of the program. The secondary phase of the program is binding. Enforcement will begin in Summer 2025, with a probationary period running until Summer 2028.[3] The tariff for the WRAP was approved by the Federal Energy Regulatory Commission in 2023.[2][4]
Two additional sharing markets, California Independent System Operator's Extended Day Ahead Market (EDAM) and Southwest Power Pool's (SPP) Markets++, will operate in adjacent areas and interoperate as needed.[5]
See also
- RTOs and ISOs
- California Independent System Operator (CAISO)
- Southwest Power Pool (SPP)
- Western Electricity Coordinating Council (WECC)
- Western Power Pool (WPP)
References
- ^ a b Seattle Utilities Consider Massive Efforts That Could Help Green Our Grid. Pacific NW Magazine, March 2023.
- ^ a b c FERC approves Western Resource Adequacy Program for regional capacity sharing. Utility Dive, Feb. 2023.
- ^ a b WRAP FAQs. Western Power Pool, April 2023
- ^ WPP Announces FERC Approval of WRAP Tariff. Western Power Pool, Feb. 2023
- ^ White Paper on WRAP Interoperability with Markets: Focus on Transfer Scenarios. Western Power Pool, June 2023
Content Disclaimer
Informasi ini disarikan dari Wikipedia dan disajikan kembali untuk tujuan edukasi. Konten tersedia di bawah lisensi CC BY-SA 3.0. Kami tidak bertanggung jawab atas ketidakakuratan data yang bersumber dari kontribusi publik tersebut.
- The information displayed on this website is sourced in part or in whole from Wikipedia and has been adapted for the purpose of restating it. We strive to provide accurate and relevant information, however:
- There is no guarantee of absolute accuracy. Wikipedia is an open, collaborative project that can be edited by anyone, so information is subject to change.
- It is not intended to constitute professional advice. The content displayed is for informational and educational purposes only. For important decisions (e.g., medical, legal, or financial), please consult a professional.
- Content copyright. Wikipedia is licensed under the Creative Commons Attribution-ShareAlike License (CC BY-SA). This means that content may be reused with appropriate attribution and shared under a similar license.
- Responsible use. Any risk arising from the use of information from this website is entirely the responsibility of the user.