Share to: share facebook share twitter share wa share telegram print page

 

Sır Dam

Sır Dam
Sır Dam is located in Turkey
Sır Dam
Location of Sır Dam in Turkey
Official nameSır Baraji
CountryTurkey
LocationKahramanmaraş Province
Coordinates37°30′2.9″N 36°35′45.35″E / 37.500806°N 36.5959306°E / 37.500806; 36.5959306
StatusOperational
Construction began1987
Opening date1991
Dam and spillways
Type of damConcrete arch
Height116 m (381 ft)
Dam volume494,000 m3 (646,128 cu yd)
Reservoir
Total capacity1,120,000,000 m3 (907,999 acre⋅ft)
Surface area48 km2 (19 sq mi)
Power Station
TypeConventional
Turbines3 x 95 MW Francis-type
Installed capacity285 MW
Annual generation725 GWh

The Sır Dam is an arch dam on the Ceyhan River in Kahramanmaraş Province of southern Turkey. There is a hydroelectric power plant, established in 1991, at the dam, with a power output of 285 MW.[1]

Involuntary Resettlement

According to Terminski (2013), the construction of the dam resulted in involuntary resettlement of approximately 45,000 people.[2]

References

  1. ^ "Sir Dam". State Hydraulic Works. Retrieved 25 November 2011.
  2. ^ Bogumil Terminski, (2013). Development-Induced Displacement and Resettlement: Theoretical Frameworks and Current Challenges, Geneva, 2013.


Kembali kehalaman sebelumnya