It was located 13 miles (21 km) upstream from the mouth of the Elwha River at the Strait of Juan de Fuca, and about 8 miles upriver from the Elwha Dam. It impounded Lake Mills reservoir. The dam was demolished in 2014 as part of the Elwha River ecosystem restoration project; as of 2015 it is the tallest dam ever to be intentionally breached. The Glines Canyon Dam was the largest dam removal ever.
History
The dam was built privately to generate electricity for industries and major military installations on the Olympic Peninsula, including lumber and paper mills in Port Angeles.
Lacking passage for migrating salmon, Glines Canyon Dam blocked access by anadromoussalmonids[5] to the upper 38 miles (61 km) of mainstem habitat and more than 30 miles (48 km) of tributary habitat. The Elwha River watershed once supported salmon runs of more than 400,000 adult returns on more than 70 miles (110 km) of river habitat. By the early 21st-century, fewer than 4,000 adult salmon returned each year.
Numerous groups lobbied Congress to remove the two dams on the river and restore the habitat of the river and its valley. The Elwha River Ecosystem and Fisheries Restoration Act of 1992 authorized the US Federal Government to acquire the Elwha Dam and Glines Canyon Dam hydroelectric power projects for decommissioning and demolition for habitat restoration.
The Elwha Ecosystem Restoration project started in September 2011 as work to demolish the nearby Elwha Dam began downstream. The final piece of the Glines Canyon Dam was removed August 26, 2014.[6] Now that the dam has been removed, the area that was under Lake Mills is being revegetated and its banks secured to prevent erosion and to speed up ecological restoration.