Together with the Hankou–Yichang and Yichang–Lichuan sections of the Huhanrong mainline, the Chongqing–Lichuan line forms what was, until the completion of the Xi'an–Chengdu high-speed railway, the only high-speed rail connection between the Sichuan Basin and the rest of China. It carries numerous high-speed trains running between the cities of the Sichuan Basin (Chengdu and Chongqing) and various destinations in the central and eastern China.
The trains are traveling on the Yuli line with the speed up to 200 km/h (120 mph). It was said that when the Yuli railway and the relevant sections of the Huhanrong mainline are completed, one would be able to travel from Chongqing to Shanghai in just 10 hours.[2] As of mid-2015, no service this fast seem to exist yet (there is no G-series train directly to Shanghai), but several D-series trains do make it from Chongqing to Shanghai in 13–15 hours.[3] There are also G-series trains running from Chongqing to Beijing (2,078 km or 1,291 mi) in 12.5 hours (G309).[3]
Construction history
Construction work started in the late 2008; the plans were for it to be completed within four years.[1] As of August 2012, it was expected that the railway will be completed by the end of 2013.[4]
Two sets of CRH2A high speed train-sets commenced testing of the completed Yuli railway line on December 11, 2013, from Chengdu to Chongqing. It was expected for the line to be opened by the end of December 2013.[5]
The Chongqing–Lichuan line was opened to conventional rail traffic at the end of December 2013, and full high speed services were expected to commence by the end of June 2014.[6]
^ ab渝利铁路今天开工 今后重庆八小时可达上海 [Construction Work on the Yuli Railway starts today. After [completion], one will be able to get from Chongqing to Shanghai in 8 hours.]. December 29, 2008.[permanent dead link]